Programme of works
Programme correct as at June 2024 and continues to be subject to change.
Sequence / order of works |
Building name |
1 | Stoneham Court |
2 | Talbot Place |
3 | Bellingham Court |
4 | Starkey Place |
5 | Gunning Place |
6 | Beadle Place |
7 | Spurrell Court |
8 | Rosemary Court |
9 | Adamson Court |
10 | Vanacker Court |
Start date:
September 2023
Estimated completion of works:
The first half of 2026